Moses Mabida Stadium
12 October 2017Mondi Paper Machine Upgrade
12 October 2017Richards Bay Mineral Link Substation Work 33kV
Project Details:
- Cables supplied directly to the value of R20 million.
- This project was for 33kV cable supply to their New Link Substation to get power closer to the dunes/Deposit far North.
- Cables were procured directly by Richards Bay Mineral and they issued the cables to their contractor to install cables.
- Duration of project: 3 Months.